Arizona Garage Builders has an evident vision to be the best RV Garage & Casita designers, and builders. From conception to the final build results, we strive to be the number one builders in all of Arizona.
Providing the highest quality designs, builds, and finished product partnered with second-to-none customer service has developed that vision into reality. We strive to exceed client expectations with every Garage & Casita we build every time, without fail.
Permits and Fees:
Blue Stake
Site:
Termite Pre-Treatment:
Grading and Excavation:
Luxe Development Group Inc DBA Arizona Garage Builders Inc. will not be held responsible for damage to or replacement of irrigation lines, sprinkler lines, water lines, gas lines, electric lines, phone lines or cable TV lines not shown on blue stake prior to excavation.
Excavation:
Excavate for foundation to plan bottom per architectural drawings and all excavated soils to be stockpiled for use during back fill. Unsuitable soil conditions at or above plan bottom are unknowns and cannot be budgeted for prior to excavation. i.e., Rock, soft clays, sinkholes, etc.
these will incur additional costs of $225 per hour.
It is unknown whether or not we will require fill dirt in order to bring your new build to meet county requirements. As such, Luxe Development Group Inc. DBA Luxe Pools and Landscaping cannot include any fill related items into the original bid, as each build and area are unique. Any fill needed to bring your project to level will be charged as a change order at $225 per hour plus $24 per ton for fill dirt.
Builder will back fill with existing excavated soils. Excess soils shall be graded out on property if possible, if not possible to grade out, expenses for hauling off-site of any excess soils will be charged to the client at $225 an hour plus dump fees.
Luxe Development Group Inc DBA Luxe Pools and Landscaping will not be held responsible for damage to or replacement of irrigation lines, sprinkler lines, water lines, gas lines, electric lines, phone lines or cable TV lines not shown on blue stake prior to excavation. If we get into a HARD DIG situation, client will be responsible for extra costs associated with hard dig.
Concrete:
Exterior Doors:
Framing:
Baseboards:
Interior Painting:
Exterior Painting:
Windows:
Roofing:
Electrical:
Plumbing:
Exterior Finish:
Insulation:
Drywall:
Garage Doors:
Epoxy:
Trenching:
For trenching and pulling of electrical lines, plumbing lines, gas lines, water lines etc. there will be a charge of $25 per ft. plus materials. This is based on having a clear run (no obstacles) such as concrete, brickwork, pavers, trees etc. this would incur additional fees at $225 per hour for labor and equipment.
Buildertrend is online as a website and also as an app for Apple and Android devices. You can use it to keep track of all the activities during your project
Your Own User panel on your phone or desktop
Pay your progress payments within the app
Always see the progress of your project’s schedule
Make change orders right from the app, easy peasy.
See images and video through out the process
Access the app 24/7 so you can be in the know
Our every client every time satisfaction guarantee gives our clients peace of mind throughout the entire garage design and build process. We are not happy if you are not satisfied with every step towards your new garage.
Reach out to our team today for a no-obligation 3D rendering and consultation.
When you hire Arizona Garage Builders you’re going to get people that will work hard to make sure that you 100% happy with your new construction project.